Permit application and approvals — submit to building department
11wPre-constructionSite prep and excavation — clearing, grading, and utilities
10wPre-constructionFoundation pour — concrete mix, rebar, and curing plan
8wPre-constructionFraming inspection — check load-bearing walls and roof trusses
6wFoundation & FramingRoof sheathing and underlayment — schedule crew and materials
5wFoundation & FramingWindows and exterior doors — order lead times and install
6wFoundation & FramingElectrical rough-in — wire, boxes, and panel installation
3wMEP & Rough-inPlumbing rough-in — DWV and water supply lines
3wMEP & Rough-inHVAC ductwork and rough-in — layout and sealing
3wMEP & Rough-inMaterial procurement schedule — order windows, doors, and roofing
12wJob site safety meeting — weekly crew briefing
14wFinal grade check — walk property with site supervisor
10wOrder lumber package for framing — studs, joists, and sheathing
11wDrywall and insulation — order materials and schedule crew
8